Freeze, gates, and locks
The switches that stop changes: freeze, which stops every plan on an environment and pauses production’s deploys, production gates, observe only, and the lock that lets one apply run at a time.
#Freeze
Freeze stops every plan on one environment, envelopes and scaling rules included, until you unfreeze it. It’s the one switch: there are no change windows.
Freeze and Unfreeze are on each environment’s row on Infrastructure, on its page, and on the repository’s settings page under Infrastructure. Each asks first:
- “Freeze production? Freezing production pauses deploys and plans; Roll back still works.”
- “Freeze staging? Freezing staging stops plans; merges still deploy here.”
While an environment is frozen:
- Every plan is refused, by the policy’s first guard. A plan that waits for you can’t be approved: “Staging is frozen: unfreeze it to approve.”
- You can still change it on the console and propose the change. Approve waits for Unfreeze.
- Drift is shown, and planned once you unfreeze. What nobody owns waits too.
- On the deploy flow, freezing production is the deploy pause: Promote and Release stop, and Roll back still works (Architect and the deploy flow).
Freeze when you want nothing to move while you look: during an incident, while you change something by hand, or before a launch. Each freeze and unfreeze is in the environment’s audit trail.
#Production gates
An environment with production gates makes every plan there wait for you, whatever your policy’s allow rules say, and makes its incidents push to your phone. A production environment has them unless you turn them off; you can give them to any other. An envelope still works under production gates: it’s bounds you approved already.
#Observe only
An observe-only environment is one the board watches and never changes: it shows what runs, its health, and its cost, and takes no desired state, plan, envelope, or apply. A file for one is refused, and nothing in it is flagged as nobody owns.
The board’s own install is always observe only, whatever the switch says. Architect never applies to it: its fix is a pull request to its code, deployed the way the board always is, and its way back is Recover without the board.
Freeze, production gates, and observe only are yours alone, from the signed-in board: the token agents and the CLI hold can’t set them.
#The lock
One apply runs at a time per environment. When a plan starts, the board takes the environment’s lock for 15 minutes and renews it while the apply works; a lock nobody renews frees itself within the hour.
While one is held, the environment’s page says which plan holds it. Another approved plan stays Approved, saying it waits for the lock, and starts once the lock is free.
Release the lock, under the environment’s status band, frees it by force. Use it only when you know the run holding it has stopped: it asks first, since the next approved plan can start at once. The release goes in the audit trail.